As far as the timeline goes we have not been able to achieve everything we wanted. The main reason for this is that the acronym button is taking much longer then expected...this is why we decided to cut out doing the 5P's, as we think it will effect the rest of the project.

Time-line Revised

Week 5 - We did get background image complete and decided that a second game was a bit ambitious.

Week 6 - Did not achieve getting the homepage complete, however this is a good thing as concept has changed.

Week 7 - Information page complete

Week 8 - Completion of safety tips not complete as acronym animations taking longer the expected.

Week 9 - Video has been edited and almost complete, however few more changes and improvements need to be done.

Week 10 - Game will not be complete in week 10 as haven't started yet, however we allowed ourselves week 11/12 to check and tidy. Also as backup in case this was to happen.